Paving and paving preparation work will continue on Boeke Road, from the Lloyd Expressway to Washington Avenue, as well as Lincoln Avenue, from U.S. 41 to Boeke.

E & B Paving, Inc. plans to begin placing asphalt along Boeke Road on August 28th and 29th. While this work is occurring, the contractor plans to mill the top 1 ½ inches of asphalt off Lincoln. E & B Paving will then finish milling and clean-up on Monday, August 31st, and pave Lincoln beginning Tuesday, September 1st.

These operations will require traffic shifts and some temporary stoppages. All traffic will be controlled by the contractor’s flagging personnel. As always, motorists are asked to drive slowly and use great caution when traveling in the vicinity and through active construction areas.